Holiday Campus Closure

University Student Union

University Student Union


18111 Nordhoff Street
Northridge, CA 91330-8272

Phone: (818) 677-2251

Send email

Social Media

Instagram | TikTok | Facebook | YouTube | LinkedIn | Flickr

Construction Updates

Friday, Dec. 6

Landscape remediation and the demolition of the pool basement slab have been completed. The roof tile installation and interior wall layout are in progress.

Valera NEST Construction as of 12/6/24

Friday, Nov. 27

Fire lane and pool deck concrete pours and high roof skylight installs have been completed. Demolition of the pool basement slab is in progress along with weather protection.

Valera NEST Construction as of Nov. 27, 2024

Friday, Nov. 15

Structural upgrades, roof installation and South Patio waterproofing continue.

Valera NEST Construction as of Nov. 15, 2024

Friday, Oct. 25

The fire water trench backfill is complete. Structural upgrades, roof installation and prepping the South Patio for waterproofing continue.

Valera NEST Construction as of 10/25/24

Friday, Oct. 18

Structural upgrades, roof waterproofing and fire water trench backfill continue.

Valera NEST Construction as of Oct. 18, 2024

Friday, Oct. 11

Structural upgrades and the fire water line installation continue. Waterproofing on the roof and South Patio deck has commenced.

Valera NEST Construction as of Oct. 11, 2024

Friday, Sept. 27

The trench for the new fire water line install as well as the interior and exterior demolition are ongoing. The backfill of the water line trench is complete and roof cutouts for skylights are in progress.

Valera NEST Construction as of 9/27/24

Friday, Sept. 20

The exterior and interior demolition are ongoing. The backfill of the first level exterior water main is ongoing and fire line trench has been laid out at the pool deck.

Valera NEST Construction as of Sept. 20, 2024

Friday, Sept. 13

The exterior and interior demolition and the trench for the new fire water line install are ongoing.

Valera NEST Construction as of Sept. 13, 2024

Friday, Sept. 6

The demolition of level one kitchen and exterior slab is ongoing.

Valera NEST Construction as of Friday, Sept. 6, 2024

Friday, Aug. 30

South exterior slab demolition and cut and cap ductwork on the interior (level one) completed. Wood framers’ material delivered.

Valera NEST Construction as of Aug. 30, 2024

Friday, Aug. 23

Demolition continues on the exterior.

Valera NEST Construction as of Aug. 23, 2024

Friday, Aug. 16

The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.

USU Valera NEST Interior Under Construction

Friday, Aug. 2 

The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.

Valera NEST Construction as of Aug. 2, 2024

Friday, July 26 

The demolition contractor completed demolition of the high roof and began demolition inside the future Valera NEST.

Valera NEST Construction as of July 26, 2024

Friday, July 19 

The contractor set up construction fencing around the Valera NEST project site and installed project signage. The demolition contractor began removing concrete roof shingles.

Valera NEST Construction Site as of July 19, 2024

University Student Union

University Student Union


18111 Nordhoff Street
Northridge, CA 91330-8272

Phone: (818) 677-2251

Send email

Social Media

Instagram | TikTok | Facebook | YouTube | LinkedIn | Flickr

Scroll back to the top of the page