Construction Updates
Friday, Oct. 25
The fire water trench backfill is complete. Structural upgrades, roof installation and prepping the South Patio for waterproofing continue.
Friday, Oct. 18
Structural upgrades, roof waterproofing and fire water trench backfill continue.
Friday, Oct. 11
Structural upgrades and the fire water line installation continue. Waterproofing on the roof and South Patio deck has commenced.
Friday, Sept. 27
The trench for the new fire water line install as well as the interior and exterior demolition are ongoing. The backfill of the water line trench is complete and roof cutouts for skylights are in progress.
Friday, Sept. 20
The exterior and interior demolition are ongoing. The backfill of the first level exterior water main is ongoing and fire line trench has been laid out at the pool deck.
Friday, Sept. 13
The exterior and interior demolition and the trench for the new fire water line install are ongoing.
Friday, Sept. 6
The demolition of level one kitchen and exterior slab is ongoing.
Friday, Aug. 30
South exterior slab demolition and cut and cap ductwork on the interior (level one) completed. Wood framers’ material delivered.
Friday, Aug. 23
Demolition continues on the exterior.
Friday, Aug. 16
The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.
Friday, Aug. 2
The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.
Friday, July 26
The demolition contractor completed demolition of the high roof and began demolition inside the future Valera NEST.
Friday, July 19
The contractor set up construction fencing around the Valera NEST project site and installed project signage. The demolition contractor began removing concrete roof shingles.