Construction Updates
Friday, Sept. 13
The exterior and interior demolition and the trench for the new fire water line install are ongoing.
Friday, Sept. 6
The demolition of level one kitchen and exterior slab is ongoing.
Friday, Aug. 30
South exterior slab demolition and cut and cap ductwork on the interior (level one) completed. Wood framers’ material delivered.
Friday, Aug. 23
Demolition continues on the exterior.
Friday, Aug. 16
The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.
Friday, Aug. 2
The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.
Friday, July 26
The demolition contractor completed demolition of the high roof and began demolition inside the future Valera NEST.
Friday, July 19
The contractor set up construction fencing around the Valera NEST project site and installed project signage. The demolition contractor began removing concrete roof shingles.